2017Completion Year
291kWInstalled Capacity
$754,925Project Cost
$175,014MCCAC Funding
342,444kWh/yearElectrical Energy Generation
219tonnes CO2e/yearGHG Reductions
Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0
As part of the MCCAC’s Alberta Municipal Solar Program (AMSP), the City of Calgary installed a 291.69 kW solar PV system at the Glenmore Water Treatment Plant. The project was completed in March 2017.
Up to date system production data can be viewed at: https://monitoringpublic.solaredge.com/solaredge-web/p/site/public?name=Glenmore#/dashboard