As part of the MCCAC’s Alberta Municipal Solar Program (AMSP), the Bow Valley Waste Management Commission through the Municipal District of Bighorn installed a 20.72 kW solar PV system on the roof of the Francis Cooke Regional Landfill Administration Building. The project was completed in August 2017.
![](https://mccac.ca/wp-content/uploads/img_5095-1-scaled.jpg)
Francis Cooke Regional Landfill Solar PV
2017Completion Year
21kWInstalled Capacity
$67,485Project Cost
$15,540MCCAC Funding
19,145kWh/yearElectrical Energy Generation
12.25tonnes CO2e/year
GHG Reductions
Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0