Lethbridge ATB Centre Solar PV

This project was funded through the Alberta Municipal Solar Program

City of Lethbridge

2019Completion Year

31kWInstalled Capacity

$143,946Project Cost

$23,250MCCAC Funding

38,400kWh/yearElectrical Energy Generation

24.58tonnes CO2e/yearGHG Reductions

Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 2.0

As part of the MCCAC’s Alberta Municipal Solar Program (AMSP), the City of Lethbridge installed a 31 kW solar PV system on the roof of the ATB Centre. The project was completed in November 2019.