Mayerthorpe Diamond Centre Retrofit

This project was funded through the TAME

Town of Mayerthorpe

2014Completion Year

$14,099Project Cost

$871Cost Savings

$7,049MCCAC Funding

8Simple Payback Period

5,213kWh/yearElectrical Energy Savings

51GJ/yearNatural Gas Energy Savings

8tonnes CO2e/yearGHG Reductions

The Diamond Centre Community Hall underwent an energy efficiency retrofit in 2014. It included a furnace retrofit, replacing the original unit with a new condensing furnace at 97% efficiency. In addition, lighting upgrades were made, with all T12 fluorescent fixtures converted to T5 fixtures, and 15W incandescent bulbs in the exit sign lighting converted to 0.8W LED bulbs.

As a result of these upgrades, the Town of Mayerthorpe is expected to save $871 in operating costs, 70 GJ of energy, and 8 tonnes of greenhouse gas emissions per year.