2013Completion Year
$10,701Project Cost
$3,003Cost Savings
$5,351MCCAC Funding
2Simple Payback Period
21,509kWh/yearElectrical Energy Savings
148GJ/yearNatural Gas Energy Savings
18tonnes CO2e/yearGHG Reductions
The Town of Redwater completed a retrofit on their Town Office in 2013. Energy saving measures included replacing manual thermostats with programmable models, replacing the weatherstripping along exterior doors and windows, and updating T12 and incandescent lighting to T8s and CFLs.
The payback period for the project is only 3.6 years, with the updates anticipated to net cost savings of $3,003, energy savings of 225 GJ, and 18 tonnes of CO2 on an annual basis.