2019Completion Year
178kWInstalled Capacity
$456,992Project Cost
$151,164MCCAC Funding
254,803kWh/yearElectrical Energy Generation
163tonnes CO2e/yearGHG Reductions
As part of the MCCAC’s Alberta Municipal Solar Program (AMSP), the Village of Stirling installed a 177.8 kW solar PV system at the Water Treatment Plant (Sewer Lift Station). The project was completed in October 2019.