Brooks City Hall Retrofit

This project was funded through TAME

City of Brooks

2012Completion Year

$1664.00Project Cost

$1986.00Cost Savings

$832.00MCCAC Funding

1Simple Payback Period

17687kWh/yearElectrical Energy Savings

9GJ/yearNatural Gas Energy Savings

9tonnes/yearGHG Reductions

The City of Brooks retrofitted their City Hall in 2012, making upgrades to the interior lighting. The lighting retrofit included delamping existing T8 fixtures throughout the building and replacing incandescent lighting with CFL flood lights. With costs of $1,664 and annual savings estimated at $1,986, the project will net an exceptional return – the payback period is only 10 months. The improvements are projected to cut energy use by 72 GJ and emissions by 12 tonnes per year.

Interested?

Read more about the TAME