2018Completion Year

$19,087Project Cost

$9,130MCCAC Funding

40,135kWh/yearElectrical Energy Savings

26tonnes CO2e/yearGHG Reductions

As part of the MCCAC’s Taking Action to Manage Energy (TAME) Express program, the Town of Bruderheim completed a high efficiency lighting retrofit of their Fire Hall. The project was completed in April 2018.