2017Completion Year

$15,128Project Cost

$5,104MCCAC Funding

12,293kWh/yearElectrical Energy Savings

8tonnes CO2e/year
GHG Reductions

Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0

As part of the MCCAC’s Taking Action to Manage Energy (TAME) Express program, the Municipal District of Provost completed a high efficiency lighting retrofit of the Municipal District of Provost Office Building in August 2017. The retrofit included a number of LED T8 Replacement Lamps and LED Troffer Fixtures.