2016Completion Year
20kWInstalled Capacity
$64,469Project Cost
$16,326MCCAC Funding
29,497kWh/yearElectrical Energy Generation
19tonnes CO2e/yearGHG Reductions
Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0
As part of the MCCAC’s Alberta Municipal Solar Program (AMSP), Northern Sunrise County installed a 20 kW solar PV system on the roof of the St. Isidore Fire Hall. The project was completed in November 2016.
Edmonton Journal: Northern Alberta fire hall powering up with solar panels, December 18, 2016