Slave Lake Public Works Shop Efficient Lighting

This project was funded through the TAME Express

Town of Slave Lake

2017Completion Year

$16,005Project Cost

$1,870Cost Savings

$6,845MCCAC Funding

18,695kWh/yearElectrical Energy Savings

12tonnes CO2e/yearGHG Reductions

Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0

As part of the MCCAC’s Taking Action to Manage Energy (TAME) Express program, the Town of Slave Lake completed a high efficiency lighting retrofit of the Slave Lake Public Works Shop. The project was completed in June 2017.