Wainwright Town Shop Retrofit

This project was funded through the TAME+

Town of Wainwright

2018Completion Year

$18,603Project Cost

$11,802MCCAC Funding

23,170kWh/yearElectrical Energy Savings

11.7tonnes CO2e/yearGHG Reductions

Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0

As part of the MCCAC’s Taking Action to Manage Energy (TAME+) program, the Town of Wainwright completed an energy efficiency retrofit of the Town Shop. The project was completed in September 2018.