As part of the MCCAC’s Taking Action to Manage Energy (TAME) Express program, the Town of Slave Lake completed a high efficiency lighting retrofit of the Slave Lake Public Works Shop. The project was completed in June 2017.
Slave Lake Public Works Shop Efficient Lighting
2017Completion Year
$6,845Rebate/Incentive
$16,005Project Cost
18,695kWh/yearElectrical Energy Savings
$1,870Cost Savings/year
12tonnes CO2e/year
GHG Reductions
Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0