As part of the MCCAC’s Taking Action to Manage Energy (TAME+) program, Wheatland County completed an energy efficiency retrofit of the Administration building. The project was completed in February 2018.
![](https://mccac.ca/wp-content/uploads/county_building-1.jpg)
Wheatland County Administration Building Retrofit
2018Completion Year
$231,900Project Cost
$51,000MCCAC Funding
110,448kWh/yearElectrical Energy Savings
940GJ/yearNatural Gas Energy Savings
69tonnes CO2e/year
GHG Reductions
Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0