As part of the MCCAC’s Taking Action to Manage Energy (TAME) Express program, the Town of Drayton Valley completed a high efficiency lighting retrofit of the Municipal Library. The project was completed in September 2017.
![](https://mccac.ca/wp-content/uploads/library-scaled.jpg)
Drayton Valley Municipal Library Efficient Lighting
2017Completion Year
$1,700Project Cost
$680MCCAC Funding
19,094kWh/yearElectrical Energy Savings
12tonnes CO2e/year
GHG Reductions
Greenhouse gas emissions reductions for this project are calculated based on Alberta’s Carbon Offset Emission Factors Handbook Version 1.0