Slave Lake Water Treatment Plant Efficient Lighting

This project was funded through the TAME Express

Town of Slave Lake

2017Completion Year

$15,082Project Cost

$1,622Cost Savings

$4,154MCCAC Funding

16,224kWh/yearElectrical Energy Savings

10tonnes CO2e/yearGHG Reductions

As part of the MCCAC’s Taking Action to Manage Energy (TAME) Express program, the Town of Slave Lake completed a high efficiency lighting retrofit of the Slave Lake Water Treatment Plant. The project was completed in June 2017.