2014Completion Year

$20,026Project Cost

$3,180Cost Savings

$10,013MCCAC Funding

3Simple Payback Period

16,665kWh/yearElectrical Energy Savings

25GJ/yearNatural Gas Energy Savings

12tonnes CO2e/year
GHG Reductions

The Vulcan Curling Club retrofit was completed in 2014, with energy saving upgrades made to the building’s interior lighting and envelope. The lighting retrofit included the conversion of 4-lamp T12 fluorescent tubes to 3-lamp T8s, 2-lamp T12s to T5s, 15W incandescent exit sign lighting to 1.4W LED bulbs, and 60-75W incandescents to 13W CFL and 6W LED bulbs. In addition, weatherstripping and sealing along exterior doors and windows was replaced. The project is expected to achieve annual savings of $3,180, 85 GJ of energy, and 12 tonnes of emissions.

Funded in part by:

Have questions?

We are here for you and your community